Buyers often assume a Chinese menswear factory needs 500 or 1,000 pieces per style. Ours starts at 100, and a first collection can be built around that number if the plan respects two constraints: fabric minimums and colourways.

Pale shirt, charcoal checked jacket, navy trousers and a leather belt laid flat on a work table
A first collection is a small number of styles done properly, not a wide range done thinly.

Four styles, 100 pieces each

A workable first range: one navy blazer, one charcoal suit, one pair of flannel trousers, one overshirt. That is 400 garments, roughly USD 20,000–28,000 FOB depending on cloth, and it fills a first season without betting the business on one silhouette.

Fabric is the real minimum

A mill will sell a stock cloth by the roll; a custom bunch may need 300–500 m. At 1.6 m per blazer that is 190–310 garments, so one custom cloth usually means one style, not four. Plan around stock bunches for the first order and save the custom bunch for the style that sells.

Colourways multiply the risk

Three colours × 100 pieces = 300 per style, and each colour is a separate dye lot with its own minimum. Two colours on the first order, one on the second, is the usual compromise. Keep the size ratio honest: XS–XXL on a 100-piece run means very few units per size, so confirm the ratio with your retail partner before the fabric is cut.

Where the cash sits

  • 30% deposit at order, which releases fabric and pattern making.
  • Sampling at cost, credited against bulk above 300 pieces per style.
  • 70% before shipment, after the inspection report.

Calendar

Brief to sample: 10–14 days including one comment round. Bulk: 25–35 days after approval. Add three weeks for sea freight to Europe and two to the US. A November decision lands on shelf in February — which is why first-season planning usually starts four months before the selling season, not eight weeks.

Questions buyers ask

Is 100 pieces per style really enough?
For a first order yes. Below 100 the fabric minimum, not the sewing, becomes the constraint.
Can we mix colours within one style?
Two colourways at 100 pieces each. A third colour adds a dye lot and a separate minimum.

Send a tech pack, a reference garment or just a photo and a size chart — we quote within one working day. How an order runs, from brief to shipment →