  1. Working back from the ship date
  2. Where the plan breaks
  3. The monthly rhythm that works
  4. What to decide early, even roughly
  5. Questions buyers ask

Spring/Summer 2027 goes on shelf from February 2027. Every date in the development calendar comes out of that one fixed point, and factories plan backwards from it. Buyers who plan forwards from “when we have the range ready” usually lose a season.

Menswear development desk with a printed season calendar, navy and charcoal fabric swatches and a tech pack folder
Season planning on the desk: the calendar is set by the ship date, not by when the brief is ready.

Working back from the ship date

Stage When What it needs
Brief and costed quote Sep 2026 Reference garment, size chart, target FOB
Fabric selection Sep–Oct 2026 Stock bunch or custom weave decision
Fit sample Oct 2026 7 days from confirmed spec
Sample approval Late Oct 2026 One or two comment rounds
Bulk Nov 2026 – Jan 2027 25–35 days per style, fabric in-house
Ship Dec 2026 – Jan 2027 Inspection, packing, FOB Shenzhen

Where the plan breaks

Two places, almost always. The first is fabric: a custom weave adds 20–30 days before cutting starts, and if that decision is taken in October the ship date moves to March. The second is the comment round: a fit sample that comes back with a shoulder change needs a re-cut and another sample, which is a week plus a week.

The monthly rhythm that works

Brief in September with a target FOB and two fabric options. Approve the sample by the end of October, at the latest in the first week of November. Place bulk so that fabric is in-house before the winter holidays, because Chinese factories close for Spring Festival in February and the January window is the last clean one.

What to decide early, even roughly

  • Two-piece versus three-piece mix, because it changes the fabric consumption per suit.
  • Size range and grading: extending to 56 later costs a pattern round.
  • Colourways: each colour is a separate dye lot and a separate fabric commitment.
  • Packaging: hanging versus flat changes carton volume and freight.

None of this is unusual. It is the same calendar every tailored brand runs, and the factories that hit February do it because the decisions were made in September, not because they worked faster in December.

Questions buyers ask

When should we brief for SS27?
September 2026 for a February delivery. Briefing in October pushes the ship date into March.
What if the fabric is custom?
Add 20 to 30 days before cutting, so the weave has to be decided by early October.